Need Help on following fields

S

ST

Hello,

Can I ask your help on the understanding the following fields.

Cost = 934K
Cummulative cost = 1044K
A difference of 110K!!!
Shouldn't the Cummulative Cost be same as Actual Cost + Remaining Cost?

Also,
Budgeted Cost = 894K
BCWS = 912K
Should these not be the same?

/Spiro Theopoulos.
 
P

Paul Conroy

cummulative cost and budgeted cost are not system fields. What formula are
you using to calculate these ?
 
S

ST

I'm sorry Paul, they are system fields.

Cummulative cost is a timephased filed.

As for Budgeted Cost, what I meant was Baseline Cost.

Any ideas on why the descrepencies in the numbers?

/Spiro.
 