Need help on how I did this in my Pivot Table

S

shcr

I did something so unusual, no one around here knows how, nor do I remember,
yet they all say, great, let me know when you figure it out!

Data is:

Activity ID Resource Budgeted Quanity

For every activity, I show each unique resource and the budgeted quantity of
each. There are about 500 rows due to approx 300 Activitiies

At the bottom I have a sum (subtotal) BY RESOURCE. Thus it adds all the
Resource codes of 2X. This is between the total of the last activity and
the Grand Total.

It IS within the pivot table, yet I cannot for the life of me find out how I
did it?


Planning FY 04 0Z 825.0
10 35.0
19 20.0
21 310.0
2R 5.0
2T 40.0
3D 560.6
3P 30.0
97 20.0
Planning FY 04 Total 1,845.6
1,845.6
0Z Sum 1,676.4
THIS PART, I CANNOT FIGURE OUT
HOW I DID IT 10 Sum 1,317.2
19 Sum 164.4
1P Sum 31.4
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top