M
Michael
Hello,
I have setup project server to send email notification
status about my project. However, the ID number of tasks
overdue shown in the email do not correlate to the actual
ID number in my MSP file. Here is an example:
From my Email:
The following tasks are overdue and incomplete.
Project: SCDR - ACR Reviesed Schedule
---------------------------------------
ID: 48 Task Name: Modify INIT for Dailer
Assign To: Ravikumar NandagapStart: 6/30/03 Finish:
7/10/03
ID: 71 Task Name: Create Witness Test Plan
Assign To: Robert Harvey Start: 7/1/03 Finish:
7/2/03
From my project file tasks 48 and 71 shown as:
Task 48 is QA Dialer 52 hrs 26.44 days Mon 6/16/03
Tue 7/22/03 40.5 hrs **This is a milestone
Task 71 is ETL Development EI Daily Delinquency 63.4 hrs
23.5 days Wed 6/11/03 Mon 7/14/03 63.4 hrs
The tasks shown in the email are tasks 47 and 114 in my
MSP file.
I have republished my project and still have the same
problem. What are my problems and how do I resolve them?
Any helps are appreciated.
Project Server/MS Project Professional
Sharepoint/SQL 2000
Michael Pham
I have setup project server to send email notification
status about my project. However, the ID number of tasks
overdue shown in the email do not correlate to the actual
ID number in my MSP file. Here is an example:
From my Email:
The following tasks are overdue and incomplete.
Project: SCDR - ACR Reviesed Schedule
---------------------------------------
ID: 48 Task Name: Modify INIT for Dailer
Assign To: Ravikumar NandagapStart: 6/30/03 Finish:
7/10/03
ID: 71 Task Name: Create Witness Test Plan
Assign To: Robert Harvey Start: 7/1/03 Finish:
7/2/03
From my project file tasks 48 and 71 shown as:
Task 48 is QA Dialer 52 hrs 26.44 days Mon 6/16/03
Tue 7/22/03 40.5 hrs **This is a milestone
Task 71 is ETL Development EI Daily Delinquency 63.4 hrs
23.5 days Wed 6/11/03 Mon 7/14/03 63.4 hrs
The tasks shown in the email are tasks 47 and 114 in my
MSP file.
I have republished my project and still have the same
problem. What are my problems and how do I resolve them?
Any helps are appreciated.
Project Server/MS Project Professional
Sharepoint/SQL 2000
Michael Pham