J
Johan
A resource (a number of interchangable persons) is
assigned at 275% to a number of FtoS linked fixed work
activities. MSP 2002.
The resources availability is 275% at all times but for
one day during which it is 185%. This is entered in the
Resource Availability list in the Resource Information
dialogue.
Now MSP shows an overallocation on the specific date with
limited resource availability, fine. I level the project
and expect the resource to work 185% on the task on the
specific date and 275% all other days. But nope, the
resource stops working completely on the specific date and
resumes work when the availability is back to 275%. (The
resource graph shows 185% available work on the specific
date)
The basic problem is very simple: A number of persons are
working on the same tasks. One of them goes on vacation
and I want the other persons to continue working (with an
increase in task duration).
When I used 3 specified resources I can understand that
the others stop working since I've explicitly pointed out
that a resource should do a certain amount of work. But
when I use a generic resource with >100% availability, it
makes me confused.
Could anyone please explain where I'm wrong and how to
solve the basic problem? I would be most grateful.
Best regards
Johan
assigned at 275% to a number of FtoS linked fixed work
activities. MSP 2002.
The resources availability is 275% at all times but for
one day during which it is 185%. This is entered in the
Resource Availability list in the Resource Information
dialogue.
Now MSP shows an overallocation on the specific date with
limited resource availability, fine. I level the project
and expect the resource to work 185% on the task on the
specific date and 275% all other days. But nope, the
resource stops working completely on the specific date and
resumes work when the availability is back to 275%. (The
resource graph shows 185% available work on the specific
date)
The basic problem is very simple: A number of persons are
working on the same tasks. One of them goes on vacation
and I want the other persons to continue working (with an
increase in task duration).
When I used 3 specified resources I can understand that
the others stop working since I've explicitly pointed out
that a resource should do a certain amount of work. But
when I use a generic resource with >100% availability, it
makes me confused.
Could anyone please explain where I'm wrong and how to
solve the basic problem? I would be most grateful.
Best regards
Johan