I’m using MS Project 2007, have several task linked with finish to start. I
have set date to schedule from, hours per day set to 8 and Working Monday
thru Friday.
My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10
Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10
Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is causing this?
Thanks in advance for your help.