Hi all!
I am using Project 2007 and Web Access to track progress in several projects
in my company. I have resources working in different projects at the same
time and they use Project Web Acess to report the amount of time (hours) they
spend in each assignment. After that, they submmit the tasks to their project
managers so they can approve their updates.

Now I'm trying to run a report that shows the sum of the "actual work" of
my resources in all projects they are assigned. I'm using the data analysis
in PWA with the data source "wlrproject Analysis Services Repository
Assignment Timephased".

The problem is that the sum of "actual work" does not match the total of
hours showed in Project Professional. We are not using "Timesheet" feature to
track hours. The resources go directly in "My tasks" in PWA and update their
tasks.

Am I doing anything wrong? Any help is very appreciated.
 