V
vincent
I need to provide a list of delivrable per project
Basic Delivrable, dates (star\finish, hour plan, hour spend, % completion,
remaining hours
So fare when I enter hours plan and spend the calculation of % completion
and remaining hour is wrong
ex 100hrs budget, 40 hrs spend, 54% and 50hrs remaining
I'm missing something
Basic Delivrable, dates (star\finish, hour plan, hour spend, % completion,
remaining hours
So fare when I enter hours plan and spend the calculation of % completion
and remaining hour is wrong
ex 100hrs budget, 40 hrs spend, 54% and 50hrs remaining
I'm missing something