I'm trying to create a reocurring task, such as submitting status reports,
that will occur twice a month (15th and 30th) from January to December.
 
S

Steve House [MS Project MVP]

Create two recurring tasks with the same name, one occuring once a month on
the 15th and the other once a month on the 30th. Alternately, a single
recurring task every other week is almost the same thing. Biweekly means
there'd be 26 reports in a year, semi-monthly means 24 - take your pick
<grin>.
 
J

JLB

If you called the Recurring task Meeting then you will end up with "Meeting
1" twice; "Meeting 2" twice ...

I'd use different task names ("Mid-month" and "End-of-month"). Other than
that, you are spot on in both your suggestions.

(BTW ... Ti-Cats can always wait until next year. Again.)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top