L
L. Davis
Hello,
Based on some searches I've done here to see if someone has already
addressed this issue, I think I know the answer...however, I would
like to float the question again in a different way just to be sure.
We need to display the WBS/Task hierarchy in the Tasks functionality
of PWA 2007. We have a time tracking view that displays a week grid
for entering actual hours spent on a task. Currently, you only see
the name of the workplan, and the subsequent tasks you are assigned to
are indented beneath it and are displayed in alphabetical order. The
order in which they are displayed in PWA is therefore not connected to
the order in which they are entered in the workplan.
Is there any way to manipulate the view to display the WBS with the
rollup tasks and correct indentation? You can see this in PWA 2003 so
I've got my fingers crossed that they didn't take this away in
2007...please let me know.
Thank you!
Based on some searches I've done here to see if someone has already
addressed this issue, I think I know the answer...however, I would
like to float the question again in a different way just to be sure.
We need to display the WBS/Task hierarchy in the Tasks functionality
of PWA 2007. We have a time tracking view that displays a week grid
for entering actual hours spent on a task. Currently, you only see
the name of the workplan, and the subsequent tasks you are assigned to
are indented beneath it and are displayed in alphabetical order. The
order in which they are displayed in PWA is therefore not connected to
the order in which they are entered in the workplan.
Is there any way to manipulate the view to display the WBS with the
rollup tasks and correct indentation? You can see this in PWA 2003 so
I've got my fingers crossed that they didn't take this away in
2007...please let me know.
Thank you!