K
Kevin Slane
I've gotten some help from the wonderful folks at MSPE on this topic in the past, but I'm still not sure of my best course of action.
I want the PM to be able to assign a task to a resource that represents a department. Our first instinct was to make this resource generic, but we want the department manager to status the tasks assigned to that department. So, we made the resource a human resource with a default assignment owner.
The problem with the above scenario is, I can't figure out a way to indicate that the resource represents multiple people, therefore, I cannot schedule that resource to work on the same task at the same time. In Project I can adjust the max units to represent something above 100%, but I cannot figure out a way to do this in Project Server.
Is this a common situation?
Kevin
Submitted via EggHeadCafe - Software Developer Portal of Choice
HTML Entities Class
http://www.eggheadcafe.com/tutorial...74-9130-3210625e675c/html-entities-class.aspx
I want the PM to be able to assign a task to a resource that represents a department. Our first instinct was to make this resource generic, but we want the department manager to status the tasks assigned to that department. So, we made the resource a human resource with a default assignment owner.
The problem with the above scenario is, I can't figure out a way to indicate that the resource represents multiple people, therefore, I cannot schedule that resource to work on the same task at the same time. In Project I can adjust the max units to represent something above 100%, but I cannot figure out a way to do this in Project Server.
Is this a common situation?
Kevin
Submitted via EggHeadCafe - Software Developer Portal of Choice
HTML Entities Class
http://www.eggheadcafe.com/tutorial...74-9130-3210625e675c/html-entities-class.aspx