John
I am interested to learn how to view Remaining Work in
Timephased Data through the Resource Usage View or the
Task Usage View. It appears that this feature is not
currently in MS Project 2000 or 2002? Correct me if I am
wrong. Also, if this feature is not available, do you
know of whether or not this has been reported to Microsft
as a feature enhancement to the software?
Timephased Data through the Resource Usage View or the
Task Usage View. It appears that this feature is not
currently in MS Project 2000 or 2002? Correct me if I am
wrong. Also, if this feature is not available, do you
know of whether or not this has been reported to Microsft
as a feature enhancement to the software?