I am interested to learn how to view Remaining Work in
Timephased Data through the Resource Usage View or the
Task Usage View. It appears that this feature is not
currently in MS Project 2000 or 2002? Correct me if I am
wrong. Also, if this feature is not available, do you
know of whether or not this has been reported to Microsft
as a feature enhancement to the software?
 
J

Jan De Messemaeker

Hi John,

Remaining work is simply equal to work beyond the date of your last update.
HTH


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 
D

Dale Howard

John --

A number of people have already answered your question in the
microsoft.public.project.pro_and_server newsgroup. Please don't cross post.
 