M
Michael Gwin
Heres my scenario:
I have 2 tasks: Migrate SQL database and Communicate SQL Migration.
Id like to put the task for communicating this migration to happen 10
working days prior to the migration.
I want the date for communicating the migration to move if the migration
date changes.
I basically want to type 2-10d in the successor field of the communication
task but Project wont let me. the communication is not a required task but I
want to see this in a list so my PM knows by which dates he needs to send out
the communication. since the plan is still being built, the actual migration
date may change (a few times) and I dont want to go check the communication
task to move it up to 10 days prior....
Any thoughts?
I have 2 tasks: Migrate SQL database and Communicate SQL Migration.
Id like to put the task for communicating this migration to happen 10
working days prior to the migration.
I want the date for communicating the migration to move if the migration
date changes.
I basically want to type 2-10d in the successor field of the communication
task but Project wont let me. the communication is not a required task but I
want to see this in a list so my PM knows by which dates he needs to send out
the communication. since the plan is still being built, the actual migration
date may change (a few times) and I dont want to go check the communication
task to move it up to 10 days prior....
Any thoughts?