M
MMMProject
I have several critical paths showing in my project and believe it is due to
each of these tasks showing either zero slack or negative slack. My questions
are as follows:
a) Should there always be only 1 critical path? If there are multiple task
collections that are at zero or negative slack would these not produce a
critical path per collection?
b) What causes negative slack? Can you please specify the exact calculation
for Total Slack? I have a task that is fixed duration (90 days) but the work
is only 9 days and it is showing with a large negative slack. I would think
this would be true only if the work could not be completed by the task end
date, but this is not the case. If it matters, this task was not in the
original baseline.
each of these tasks showing either zero slack or negative slack. My questions
are as follows:
a) Should there always be only 1 critical path? If there are multiple task
collections that are at zero or negative slack would these not produce a
critical path per collection?
b) What causes negative slack? Can you please specify the exact calculation
for Total Slack? I have a task that is fixed duration (90 days) but the work
is only 9 days and it is showing with a large negative slack. I would think
this would be true only if the work could not be completed by the task end
date, but this is not the case. If it matters, this task was not in the
original baseline.