A
Arthur Darr
Has anyone ever encountered negative values for BCWP, BCWS, and EAC? These
are small tasks, less than 80 hours. In progress tasks have negative BCWP, as
well. This only affects a handful of tasks. Re-baselining the tasks do not
solve the problem. In addition, the "correct" EAC is around 5,000 hours, the
displayed, project level EAC is, get this, negative 866 million. This
project is on project server.
are small tasks, less than 80 hours. In progress tasks have negative BCWP, as
well. This only affects a handful of tasks. Re-baselining the tasks do not
solve the problem. In addition, the "correct" EAC is around 5,000 hours, the
displayed, project level EAC is, get this, negative 866 million. This
project is on project server.