L
Laureen
Hello,
The duration variance calculates negatively when a task/project finishes
ahead of schedule. For example, Baseline Duration is 90 days. Actual
Duration is 60 days. Duration variance becomes -30 days. Is there a way to
flip this and have the variance expressed positive?
Thanks,
Laureen.
The duration variance calculates negatively when a task/project finishes
ahead of schedule. For example, Baseline Duration is 90 days. Actual
Duration is 60 days. Duration variance becomes -30 days. Is there a way to
flip this and have the variance expressed positive?
Thanks,
Laureen.