I'm taking a PM class and our instructor had us manually create a network
diagram so that we could learn how the forward pass and backward pass are
calculated. He also said that the network diagram in project can be
configured to show the calculations as well. For example... 0 10 Days
Duration 10 instead of dates. I have figured out how to reflect this in
diagram box but cannot get it to add the ten days to the duration on the
following box. I created a custom number field with a formula to get it to
show what is in the example based on my tasks. Any one know how to get the
print out to show as it would if it were manually calculated? Thanks!
diagram so that we could learn how the forward pass and backward pass are
calculated. He also said that the network diagram in project can be
configured to show the calculations as well. For example... 0 10 Days
Duration 10 instead of dates. I have figured out how to reflect this in
diagram box but cannot get it to add the ten days to the duration on the
following box. I created a custom number field with a formula to get it to
show what is in the example based on my tasks. Any one know how to get the
print out to show as it would if it were manually calculated? Thanks!