B
Baggy
I have a plan with over 400 tasks which is split into a number sections.
When I view the plan as a Network Diagram it show all the task/subtasks from
start to finish of the Project. Is it possible to just to select what can be
displayed as a Network Diagram.
If so, I'd like to be able to (i) select particular tasks/subtasks e.g. line
40 to 70 to be shown only (ii) select a timescale e.g. 1 February to 1 April
to be shown only.
Any advice would be greatly appreciated.
When I view the plan as a Network Diagram it show all the task/subtasks from
start to finish of the Project. Is it possible to just to select what can be
displayed as a Network Diagram.
If so, I'd like to be able to (i) select particular tasks/subtasks e.g. line
40 to 70 to be shown only (ii) select a timescale e.g. 1 February to 1 April
to be shown only.
Any advice would be greatly appreciated.