Network Diagrams - PERT view

C

Chipman

I am trying to get the tasks within MSP network diagram view to display in
the format

Early start, Early Finish
Late Start, Late Finish
Duration, Float,
Task Name.

As in the visio PERT format, but am struggling to see how tof ormat the task
boxes?
 
J

Jan De Messemaeker

Hi Chipma,n,

Here we go:

Format, Box Styles, More Templates, New
Make your template than assign it to the appropriate categories Critical,
non critical, etc.
Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
C

Chipman

Thanks,

Tried to do that but didn't get it looking how i wanted. i.e. title then
value etc? Will have another go though. At least i know there isn't a
pre-determined style, which i thought there would be so i can at least stop
looking!
 