'New and Changed' indicator 'Stuck.'

V

vandermt

We are using project server 2003.

One of our project managers has made changes to a published project. These
changes were primarily in start and finish dates. After making these changes
the 'new and changed' indicator is displayed for thoses tasks.

The problem is we cannot get the 'new nad changed' indicator to reset (clear).

We have tried rebublish 'all information', 'new and changes assignments',
'project plan' and 'republish assignments.'

Nothing seams to clear the indicator.
What could have caused the problem?
How can we clear it?

Thanks
 
M

Marc Soester [MVP]

Hi vandermt,

what is the "New and Changed" indicator? sounds like a custom field with
some formula behind it. It would be great if you could profide more detailed
information.
thanks
 
V

vandermt

Marc,
Sorry for not being clear.
I am talking about the envolope with the exclamaition mark in the indicator
column. (Information has changed)
 