Jeffrey
I've gone under Tools > Change Working Time and created a new calendar, 50 hr
Work Week. I've gone under Work Weeks > Details, and changed the working
times from M-F, 6:00 AM to 12:00 PM and 1:00 PM to 5:00 PM. I've gone under
Tools > Options > Calendar, and changed the Default Start and End times
accordingly. Under Project > Project Information, I've assigned as the
project calendar. I've created one task, Mobilization, and made that start
per the project start date under Project Information, with a Duration of 1
day. The task shows as starting on Monday, but ending on Tuesday.
If I use the Standard Calendar, create the same single task, give it a
Duration of 1 day, and start it on the same date it starts and ends on Monday
correctly.
What am I doing wrong?
Work Week. I've gone under Work Weeks > Details, and changed the working
times from M-F, 6:00 AM to 12:00 PM and 1:00 PM to 5:00 PM. I've gone under
Tools > Options > Calendar, and changed the Default Start and End times
accordingly. Under Project > Project Information, I've assigned as the
project calendar. I've created one task, Mobilization, and made that start
per the project start date under Project Information, with a Duration of 1
day. The task shows as starting on Monday, but ending on Tuesday.
If I use the Standard Calendar, create the same single task, give it a
Duration of 1 day, and start it on the same date it starts and ends on Monday
correctly.
What am I doing wrong?