Hi,

When the administrator change the project manager of one project and project
is republished by the new manager.

but when the team members create a new tasks and update them . these tasks
are still going to the previous manager . Although the new manager trying
republish various time but these tasks are not coming to the new manager .
although the team member entering hours in old tasks .
those old tasks are going to the new manager but when the team members make
new tasks these new tasks are always go towards old manager .
pls tell me the solution of this problem.

regards

Micheal
 
C

Carl Dalton

try Republishing with the box ticked for Become the Manager of these
Assignments....

..... should do it!! ;)
 
R

Ray McCoppin

There are two different items that project will send tasks assignment updates
to. The project owner and the project manager of the task. All new task
will be sent to the project owner all other task are sent to the project
manager that published that task. If you want new task to go to someone
else. An administrator needs to change the owner of the project. This is
done by an administrator using the PWA edit project button in the project
center.

Hope this helps.
 