ProjectAnalyst
I'd like to change our current enterprise calendar. We currently use a 35
hour per week calendar, and would like to go to 40 hours per week.
Now, I could simply go in and change the hours in the enterprise calendar,
but I suspect the schedule changes would be dramatic.
Maybe a new 40 hour per week calendar applied to all resources would work
better?
Any thoughts on a good approach? Thanks.