New finish date must occur after start date and between 1/1/1984 a

M

Mousa

hi to all,

New finish date must occur after start date and between 1/1/1984 and
12/31/2049
when one of my team member try to update complete work this message appear

can anyone help me
 
B

Ben Howard

Hi, check the start date of the task, and make sure that the date the users
is inputting is after that.
 
M

Mousa

thanx ben but
i try this but it still not work the same error appear
my task in the project plan its from 11/6/2007 to 11/6/2007
and the task appear same in my task page
this mean that is 2 day when i set the complete work to 1 or 2 day the error
appear.
 
R

ROS

Verify the Task type. If the Task type is a Fixed Duration, then the user
must log actual work that will satisfy the Fixed duration. This usually
means the actual work equals the scheduled work.
 
M

Mousa

Thank you ros i will check it and confirm thanx

ROS said:
Verify the Task type. If the Task type is a Fixed Duration, then the user
must log actual work that will satisfy the Fixed duration. This usually
means the actual work equals the scheduled work.
 