Have been working on and off with project for last 8 years.. New project to
manage.. Adding dump bodies to truck frames... 300 trucks, 5 basic tasks
1. Frame setup 3h
2. Electrical 5h
3. Hydraulics 6h
4. Add Dump Body 3h
5. Testing 2h
truck moves to specified areas of work as avail.
Would also like to include detail subtasks..
Would Master / Sub Project work?