Bill Meacham
New projects are not picking up all the settings in the Enterprise Global
template.
I had up a version of the Enterprise Global in which the default scheduling
options were Fixed Units and Effort-Driven (in Tools / Options / Schedule).
Projects created with this version of Enterprise Global had their task
options set this way. I backed up this version of Enterprise Global.
Then I changed the options in Enterprise Global to Fixed Duration and not
Effort-Driven. Projects created with this version had their task options set
the new way.
Then I restored the earlier version of the Enterprise Global and closed
Project and re-opened it. I have verified that the Enterprise Global options
are now set to Fixed Units and Effort-Driven. But new projects still have
their task options set to Fixed Duration and not Effort-Driven! What do I
need to do to get new projects to pick up the Enterprise Global settings here?
template.
I had up a version of the Enterprise Global in which the default scheduling
options were Fixed Units and Effort-Driven (in Tools / Options / Schedule).
Projects created with this version of Enterprise Global had their task
options set this way. I backed up this version of Enterprise Global.
Then I changed the options in Enterprise Global to Fixed Duration and not
Effort-Driven. Projects created with this version had their task options set
the new way.
Then I restored the earlier version of the Enterprise Global and closed
Project and re-opened it. I have verified that the Enterprise Global options
are now set to Fixed Units and Effort-Driven. But new projects still have
their task options set to Fixed Duration and not Effort-Driven! What do I
need to do to get new projects to pick up the Enterprise Global settings here?