J
Jay Carter
I have seen many threads discussing how to create custom fields with
graphical indicators that can be displayed in PWA. But I haven't seen this
one...
I want to create a custom field with the red/yellow/green stoplight
indicator to show budget status. I want this to appear in a view in Project
Center. When I create views in PWA for Project Center, the only custom fields
I can select are Enterprise Project fields (like Enterprise Project Cost1) or
non-enterprise task fields (like Number1, Text1, etc.).
Since I want all projects in Project Server to have this budget status, I
would like to use an Enterprise Project field.
The first step then is to open the Enterprise Gobal and open Customize
Enterprise fields and select Enteprise Project Cost 1 and, for the sake of
simplicity, just make a formula and make it equal to the [Cost Variance]
field. (I will worry about the graphical indicators later.) Save it, close it.
Now when I go to a new project and put in some numbers, then baseline it,
then put in some actuals, I don't get the results I want. I either get #ERROR
or 0, depending on the options I select for "Calculation for task and group
summary rows" back in the Enterprise Global.
So, I think that what I am trying to do is not possible. All of the examples
I have seen either have a person creating a non-enterprise custom field or
enter values manually into the Enteprise Project field. But what I am trying
to do seems to me to be logical and viable, but I'm just not getting there.
Any suggestions or comments? It would help even if someone said I was
looking in the wrong place entirely.
graphical indicators that can be displayed in PWA. But I haven't seen this
one...
I want to create a custom field with the red/yellow/green stoplight
indicator to show budget status. I want this to appear in a view in Project
Center. When I create views in PWA for Project Center, the only custom fields
I can select are Enterprise Project fields (like Enterprise Project Cost1) or
non-enterprise task fields (like Number1, Text1, etc.).
Since I want all projects in Project Server to have this budget status, I
would like to use an Enterprise Project field.
The first step then is to open the Enterprise Gobal and open Customize
Enterprise fields and select Enteprise Project Cost 1 and, for the sake of
simplicity, just make a formula and make it equal to the [Cost Variance]
field. (I will worry about the graphical indicators later.) Save it, close it.
Now when I go to a new project and put in some numbers, then baseline it,
then put in some actuals, I don't get the results I want. I either get #ERROR
or 0, depending on the options I select for "Calculation for task and group
summary rows" back in the Enterprise Global.
So, I think that what I am trying to do is not possible. All of the examples
I have seen either have a person creating a non-enterprise custom field or
enter values manually into the Enteprise Project field. But what I am trying
to do seems to me to be logical and viable, but I'm just not getting there.
Any suggestions or comments? It would help even if someone said I was
looking in the wrong place entirely.