Badger02
When using Server and adding a resource to an effort driven task, the total
work on that task does not seem to stay the same. For instance, one resource
had 16 hours on an effort driven task (at 30% load). Another resource added
8 hours to that task with the assumption that the first resource would have
his hours reduced by 8 hours. Project instead reduced the hours to 3.7 for
the first individual, making the total work 19.7 hours. I want the total
work on the task to stay constant, how can I do this while using Server? I
have tried both fixed work and Fixed Units - Effort Driven. Thanks,
work on that task does not seem to stay the same. For instance, one resource
had 16 hours on an effort driven task (at 30% load). Another resource added
8 hours to that task with the assumption that the first resource would have
his hours reduced by 8 hours. Project instead reduced the hours to 3.7 for
the first individual, making the total work 19.7 hours. I want the total
work on the task to stay constant, how can I do this while using Server? I
have tried both fixed work and Fixed Units - Effort Driven. Thanks,