J
Jag
SP2a has been installed for Project Server 2003. When a new resource is added
to MS Project Server 2003, there are notification on the resource's home page
stating that there are unsubmitted timesheets for weeks prior to the date of
join for that resource. The SP2a claims to have fix this issue. Is this
because the resource has been assigned to tasks that start even before the
date of join to this new resource? Is there a work around for this issue?
to MS Project Server 2003, there are notification on the resource's home page
stating that there are unsubmitted timesheets for weeks prior to the date of
join for that resource. The SP2a claims to have fix this issue. Is this
because the resource has been assigned to tasks that start even before the
date of join to this new resource? Is there a work around for this issue?