J
James
I have a task to which I have assigned a resource. However I want this
resource to work on another item as well for part of the time and then
continue to work on this task 100%.
How do I set this up in project 2003?
my task is develop code - my resource is developer - I want him to work 50%
on the task for 5 days and then 100% for 3 days. I have a second resource
also allocated to this task - developer 2 - and he is allocated 100% to this
task.
Any help would be greatly appreciated.
resource to work on another item as well for part of the time and then
continue to work on this task 100%.
How do I set this up in project 2003?
my task is develop code - my resource is developer - I want him to work 50%
on the task for 5 days and then 100% for 3 days. I have a second resource
also allocated to this task - developer 2 - and he is allocated 100% to this
task.
Any help would be greatly appreciated.