Greeting,
I'm not understand a thing in MSP 2007 PWA assignement tasks process. I
have project and my role in it - PM. I'm adding 6 tasks for my team member
and publish this assignments. When I'm visiting PWA I'm see at Reminders ->
Tasks

message:

" You have 6 new tasks assigned to you."

In my tasks section I see all this tasks but they are assigned to the my
team member.
And I've also recived allerts and tasks wirh outlook add-in

Is this a bug or feature?

Best regards,
Alexander Barvinsky
http://pm4pm.org
 
G

Gary L. Chefetz [MVP]

Your resources need to have their default assignment owner set to themselves
to avoid this in the future. For the existing project, you need to insert
the Assignment owner field into the view and set it there. In the future,
please post Project Server questions to the microsoft.public.project.server
newsgroup.

--

Gary L. Chefetz, MVP
MSProjectExperts
For Project Server Consulting: http://www.msprojectexperts.com
For Project Server FAQS: http://www.projectserverexperts.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top