J
Jim Sipe
We are running Project Server 2007 and Project Profesional 2007 with the
latest server packs.
A user requests a "New Task" from their "My Tasks" PWA page. The Project
Manager accepts this NewTask and it gets added to the Project Schedule. If
the Project Manager then Resource Levels the schedule, that "New Task" gets
moved out in time for no apparent reason. It is as if extra delay has been
added without the knowledge of the Project Manager.
Any clues or reasons on why this is happening?
latest server packs.
A user requests a "New Task" from their "My Tasks" PWA page. The Project
Manager accepts this NewTask and it gets added to the Project Schedule. If
the Project Manager then Resource Levels the schedule, that "New Task" gets
moved out in time for no apparent reason. It is as if extra delay has been
added without the knowledge of the Project Manager.
Any clues or reasons on why this is happening?