P
Paul
I can't figure out why newly added tasks to my established plan are given a start date in the past
I've set up my plan using Work, Predecessors & Resource assignments exclusively (i.e. no fixed dates). When the week is through, I enter everyone's actual time in the Resource Usage sheet. If someone works less then 8 hours a day, I change the working time to the number of hours worked
I'm using the Level by "Priority, Standard" option. I use prority to keep tasks together. I've set the priority of my new task to be the same as tasks currently in-progress. When I run the leveling, it starts the task two months in the past. So I looked at the day it started the task, and the resource was fully allocated for the day in question. After the leveling, the resource picked up an additional .47 hrs for the day. (9.47 now displayed in red). As far as resource allocation % goes, I have resources assigned 100% to a single task at a time.
I've set up my plan using Work, Predecessors & Resource assignments exclusively (i.e. no fixed dates). When the week is through, I enter everyone's actual time in the Resource Usage sheet. If someone works less then 8 hours a day, I change the working time to the number of hours worked
I'm using the Level by "Priority, Standard" option. I use prority to keep tasks together. I've set the priority of my new task to be the same as tasks currently in-progress. When I run the leveling, it starts the task two months in the past. So I looked at the day it started the task, and the resource was fully allocated for the day in question. After the leveling, the resource picked up an additional .47 hrs for the day. (9.47 now displayed in red). As far as resource allocation % goes, I have resources assigned 100% to a single task at a time.