New Tasks are not obtained with AssignmentGet

J

JK

Hi All,

I was able to get all the old assignment details. But I am not
getting the new assignments. Earlier I had a problem of tasks being
read only in PWA. Then I made some changes in the admin module in
Customize Microsoft Project Web
Access" --> Specify the default method for reporting progress on tasks,
I got all the tasks in editable mode. But now I am not getting the new
tasks with the "<AssignmentsGet>" method. The MSP_WEB_ASSIGNMENTS table
contains the entry for this new assignments and also all these
assignments are appearing in the PWA. But with <AssignmentsGet> PDS
Method I am not getting the new assignments. Pls help me on this.

Thanks in Advance

Regards

Jose
 
E

Ed Morrison

Before you do the AssignmentsGet method, did you publish and close project?
Also, the publishing operation is not instantaneous and can take some time.
 
J

JK

Hi Morrison,

I figure out the problem. When we send the Request to the Webserver,
it is putting some date ranges automatically. All of my assignments was
out of that range. Thats why I was not able to retrieve data. When we
pass the date ranges, PDS fetches the data. Thanks for your response.

Reg
Jose
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top