New Tasks on View Resource Assignments

L

LAUREEN.

We do not use the timesheets to capture actuals. But, Resource Managers
still want to use the "View Resource Assignments" to see what tasks the
resources are working on.

I am trying to clean up the older projects by republishing them. Tasks that
are now 100% complete are showing up as new. But they are not new, any ideas?

Thanks.
 
R

Robert

Hi Laureen,

The Green icon means that the task was added since the last time that the
user viewed it. Should disappear and if you have current tasks only filtered
in the My Tasks view that should help. Make sure you have defined what a
current task is under the Server Settings / Tasks Settings Display / Define
Current Tasks


--
Project Consultant

REJ Company

(e-mail address removed)
 