New to Project! How to link split tasks?

I

I_Need_Help

Hi
I have a task that runs for two weeks then after one week another task is
added that requires me to pause the existing task and start the new task
then I return to the remaining part of the original task.

So I split the original task and want to link from within the split out to
the new task and then from the new task back down to the remaining part of
the split task!

I hope this makes sense!


Also how do I import and from where the calendar with bank holidays in it?

many thanks
 
D

Dale Howard [MVP]

I Need Help --

You cannot link to/from task splits. I would recommend that you break this
situation into three tasks, such as:

Task A
Task B
Task A Continues

Link them with a Finish-to-Start dependency. Hope this helps.
 
M

Mike Glen

Hi Adrian,

Welcome to this Microsoft Project newsgroup :)

Housatonic has a free program to import holidays - Google for it.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
I

I_Need_Help

Unfortunately the Housatonic application doesn't install on vista :(

Any others? or any one got it installed and can post the files?


thanks
 
M

Milan Bortel

Hey guys,

thanks for answering this question, I was looking for importing bank
holidays to Project as well.

MiB
--
Milan Bortel

MCAS, MCTS
GOPAS Computer Training Center
Brno, Czech Republic
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top