D
devbro
I must schedule the design of hundreds of tools - many with different
durations. I have three tool designers. The schedule start and complete
of each tool are constrained and must start and complete on a fixed date
(fixed duration / not effort driven). How can Project allocate and level
load the resources for me?
Must I assign all three resources to each task and then level?
Can Project spread the resources over all the tasks for me?
thanks.....
durations. I have three tool designers. The schedule start and complete
of each tool are constrained and must start and complete on a fixed date
(fixed duration / not effort driven). How can Project allocate and level
load the resources for me?
Must I assign all three resources to each task and then level?
Can Project spread the resources over all the tasks for me?
thanks.....