A
Ashley McKown
hello everybody
here is the deal i work as a production manager for a steel parts
manufacturing company.
We manufacture several parts but all in all around hundred. I decided to
use ms project to better manage resources but more importantly for scheduling
each task and resource.
The way i designed it so far, and i will appreciate everyone's input in that
as well, is I created a different project for each part and then i created a
project in which I will create the resource pool and will import all the
projets that are in the order list for the day. Now here is the problem,
number 1, I want that when i import projects each project should ask me what
is the "deadline" and also i want to introduce a macro that will ask for the
"partrs ordered" and then it will calculate the fixed costs such as manpower
hours and raw material required. Like for example each metal sheet makes 2
parts so if the order is of 100 parts the macro should calculate that it
requires 50 sheets and it should display that in the summary bar and then the
task 1-3 will use machine 2,3 and 4 to for two hours each and each machine
will require two operators which means 4 manpower hours for each machine and
12 for the whole project. How do i go about doing that, any kind of help
will be greatly appreciated, by the way i have no programming experience
whatsoever. Here is another problem when i created a project for each
project separately, lets say task number one took 2 hours and task number two
took two hours and so on and so forth, the way project is scheduling it that
it will push the task into next day rather than keepign it in the same day
just one after the other. Here is another one we only give half hour lunch
breaks and my shifts starts at 7:30 in the morning but in the gant chart
timescale i can either show it as starting at 7 or 8. Also how do i set the
task up so that when each task is due (like 9am) i can input whether the task
was completed and if not when it was completed.
This would be it for now. I was told by circuit city where i bought the
software from that people on this board are very helpful and there are
answers to everything that can be done in the project on this board so if u
guys can help this technology challenged female production manager out it
will be greatly appreciated.
thanking in advance.
ash
here is the deal i work as a production manager for a steel parts
manufacturing company.
We manufacture several parts but all in all around hundred. I decided to
use ms project to better manage resources but more importantly for scheduling
each task and resource.
The way i designed it so far, and i will appreciate everyone's input in that
as well, is I created a different project for each part and then i created a
project in which I will create the resource pool and will import all the
projets that are in the order list for the day. Now here is the problem,
number 1, I want that when i import projects each project should ask me what
is the "deadline" and also i want to introduce a macro that will ask for the
"partrs ordered" and then it will calculate the fixed costs such as manpower
hours and raw material required. Like for example each metal sheet makes 2
parts so if the order is of 100 parts the macro should calculate that it
requires 50 sheets and it should display that in the summary bar and then the
task 1-3 will use machine 2,3 and 4 to for two hours each and each machine
will require two operators which means 4 manpower hours for each machine and
12 for the whole project. How do i go about doing that, any kind of help
will be greatly appreciated, by the way i have no programming experience
whatsoever. Here is another problem when i created a project for each
project separately, lets say task number one took 2 hours and task number two
took two hours and so on and so forth, the way project is scheduling it that
it will push the task into next day rather than keepign it in the same day
just one after the other. Here is another one we only give half hour lunch
breaks and my shifts starts at 7:30 in the morning but in the gant chart
timescale i can either show it as starting at 7 or 8. Also how do i set the
task up so that when each task is due (like 9am) i can input whether the task
was completed and if not when it was completed.
This would be it for now. I was told by circuit city where i bought the
software from that people on this board are very helpful and there are
answers to everything that can be done in the project on this board so if u
guys can help this technology challenged female production manager out it
will be greatly appreciated.
thanking in advance.
ash