M
Michael T
Many eons ago using an early version of Project, I could enter tasks of 30, 45,
60, 75 days, etc., duration to mean a month, month-and-a-half, etc., and the
program understood I meant for these time blocks to span non-working days
(weekends); so for example, a "30-day" task entered on May 1 would finish June 1.
Fast-forward to the present day, and my Project 2007 interprets "30 days" to
mean 30 *work* days rather than 30 calendar days.
How can I use 30/45/60/75 etc., again and get the durations I used to? A few
googlings hinted this'd be a setting in Tools> Options, but nothing there jumps
out.
Grateful for any clues or pointers to a good newbie FAQ.
Michael
60, 75 days, etc., duration to mean a month, month-and-a-half, etc., and the
program understood I meant for these time blocks to span non-working days
(weekends); so for example, a "30-day" task entered on May 1 would finish June 1.
Fast-forward to the present day, and my Project 2007 interprets "30 days" to
mean 30 *work* days rather than 30 calendar days.
How can I use 30/45/60/75 etc., again and get the durations I used to? A few
googlings hinted this'd be a setting in Tools> Options, but nothing there jumps
out.
Grateful for any clues or pointers to a good newbie FAQ.
Michael