C
Craig
Hello all,
I am setting up a project that will take a set
implementation plan that is duration (date)
driven.Resources will be assigned but for sorting and
status reporting only. Then duplicate it to 4 different
areas of our plant. The plan consists of 4 Summary tasks
with each task based on a start/finsh relationship. On the
completion of Sum.task #1 i would like to start the second
area. As the second area completes Sum.task #1 then start
the 3rd area and so on.
I would like to set up a master plan that would allow me
track and modify any variations to the finish date of each
area and to the overall finsish date of the project.
Any advice on the most efficient way to do this would be
greatly apreciated,
Thanks...Craig
I am setting up a project that will take a set
implementation plan that is duration (date)
driven.Resources will be assigned but for sorting and
status reporting only. Then duplicate it to 4 different
areas of our plant. The plan consists of 4 Summary tasks
with each task based on a start/finsh relationship. On the
completion of Sum.task #1 i would like to start the second
area. As the second area completes Sum.task #1 then start
the 3rd area and so on.
I would like to set up a master plan that would allow me
track and modify any variations to the finish date of each
area and to the overall finsish date of the project.
Any advice on the most efficient way to do this would be
greatly apreciated,
Thanks...Craig