B
Bob
Here's what I think leveling should do... I have 3 Summary tasks each with
dozens of tasks underneath. Each sub-task is set to "As Soon As Possible",
duration from 2h to 5d with no constraints. Total project hours about 2000
(1 year). I have one resource allocated to summary tasks as follows:
Summary Tasks:
Management - 15%
Development - 15%
Marketing - 70%
When I level the project, shouldn't the project completion date be pushed
out for one year? Shouldn't each task be stretched-out based on how the
resource time is being divided?
None of the dates or durations are being adjusted at all. All "leveling"
does is calculate the number of hours each summary task will receive from
the one resource. How do I get it to adjust task start times/durations and
estimate project completion dates?
Thanks, -Bob
MS Project 2000
dozens of tasks underneath. Each sub-task is set to "As Soon As Possible",
duration from 2h to 5d with no constraints. Total project hours about 2000
(1 year). I have one resource allocated to summary tasks as follows:
Summary Tasks:
Management - 15%
Development - 15%
Marketing - 70%
When I level the project, shouldn't the project completion date be pushed
out for one year? Shouldn't each task be stretched-out based on how the
resource time is being divided?
None of the dates or durations are being adjusted at all. All "leveling"
does is calculate the number of hours each summary task will receive from
the one resource. How do I get it to adjust task start times/durations and
estimate project completion dates?
Thanks, -Bob
MS Project 2000