S
sgonzalez
I am working on a project where all in progress tasks need
to take into account the passage of time. When we go from
one meeting day to the next, in essence 2 wks have passed.
So all in progress tasks need to add 2 wks to the
remaining duration, with out effecting the percent
complete. For our use, the percent complete is used to
keep track of tasks (within the task) not the duration of
the task or the percentage of work left to be completed.
What can I do?
to take into account the passage of time. When we go from
one meeting day to the next, in essence 2 wks have passed.
So all in progress tasks need to add 2 wks to the
remaining duration, with out effecting the percent
complete. For our use, the percent complete is used to
keep track of tasks (within the task) not the duration of
the task or the percentage of work left to be completed.
What can I do?