K
Kevin
Hi, I've been pouring over old posts and can't find an answer. Maybe I
came across it and didn't understand, so if so, I appologize in
advance.
The quick question:
Without defining Predecessors and not setting deadlines, is it possible
to set a task to be the final task within a subgroup?
The reason why:
I have a bunch of tasks in a subgroup (call it "Phase 1") defining the
critical path in my schedule. I would like to set up a milestone
markers within "Phase 1" to indicate when an external task should be
complete by. These markers should be the very last tasks occuring with
"Phase 1", but should not drive its duration. This could easily be
done with Predecessors, but would require lots and lots of them to
ensure that it is indeed the last task within "Phase 1." It would work
but be very ugly.
Thanks for any help,
Kevin
came across it and didn't understand, so if so, I appologize in
advance.
The quick question:
Without defining Predecessors and not setting deadlines, is it possible
to set a task to be the final task within a subgroup?
The reason why:
I have a bunch of tasks in a subgroup (call it "Phase 1") defining the
critical path in my schedule. I would like to set up a milestone
markers within "Phase 1" to indicate when an external task should be
complete by. These markers should be the very last tasks occuring with
"Phase 1", but should not drive its duration. This could easily be
done with Predecessors, but would require lots and lots of them to
ensure that it is indeed the last task within "Phase 1." It would work
but be very ugly.
Thanks for any help,
Kevin