M
Mark Jerde
Sorry if this is an FAQ I missed here:
http://www.mvps.org/project/faqs.htm
MS Project Professional 2003.
I'm using Project to come up with the total effort for a job we're getting
ready to bid on. I'm nearing completion of listing all the tasks & subtasks
and assigning guesstimates of the time each subtask will take. I'm trying
to find a report that will give the total hours for each task & subtask, but
so far I haven't found it. Take the Level 2 task and its subtasks below:
Develop Grommet Interface Software
Acquire Two Grommet Implementations 2 days
Analysis / Design 1 wks
Implement Phase 1 2 wks
Implement Phase 2 2 wks
I'm looking for a report that has the total time summed up:
Develop Grommet Interface Software 23 days
(Assuming my addition is correct. <g>)
The last time I did this I gave up and copied everything to Excel, where I
know how to sum. I'd really like to figure out how to do it in Project,
because it's likely there will be several rounds of changes as we staff it
prior to bid.
Thanks in advance.
-- Mark
http://www.mvps.org/project/faqs.htm
MS Project Professional 2003.
I'm using Project to come up with the total effort for a job we're getting
ready to bid on. I'm nearing completion of listing all the tasks & subtasks
and assigning guesstimates of the time each subtask will take. I'm trying
to find a report that will give the total hours for each task & subtask, but
so far I haven't found it. Take the Level 2 task and its subtasks below:
Develop Grommet Interface Software
Acquire Two Grommet Implementations 2 days
Analysis / Design 1 wks
Implement Phase 1 2 wks
Implement Phase 2 2 wks
I'm looking for a report that has the total time summed up:
Develop Grommet Interface Software 23 days
(Assuming my addition is correct. <g>)
The last time I did this I gave up and copied everything to Excel, where I
know how to sum. I'd really like to figure out how to do it in Project,
because it's likely there will be several rounds of changes as we staff it
prior to bid.
Thanks in advance.
-- Mark