L
Linda
I've inherited a Project schedule with some tasks
scheduled to take .5 days. I entered scheduled durations
and let Project calculate all dates but the first task's
start date. When I enter actual dates, I'm getting changes
in duration, even when the dates I enter are the same as
the scheduled dates. All .5 days change to 1 day. I still
get problems when I test changing the scheduled durations
to 1 day. I have a 1 day task with actual start and end on
July 12. But since it's really a half day task, the next
task's actual start is also July 12, and the actual finish
is July 13. Project is saying this is 2 days' duration,
and showing a 1 day variance. I would have thought it
would consider this task to take less, not more, time than
scheduled. What do I need to change to make .5 days work,
and avoid that change to 2 days' duration?
scheduled to take .5 days. I entered scheduled durations
and let Project calculate all dates but the first task's
start date. When I enter actual dates, I'm getting changes
in duration, even when the dates I enter are the same as
the scheduled dates. All .5 days change to 1 day. I still
get problems when I test changing the scheduled durations
to 1 day. I have a 1 day task with actual start and end on
July 12. But since it's really a half day task, the next
task's actual start is also July 12, and the actual finish
is July 13. Project is saying this is 2 days' duration,
and showing a 1 day variance. I would have thought it
would consider this task to take less, not more, time than
scheduled. What do I need to change to make .5 days work,
and avoid that change to 2 days' duration?