K
Kevlin
Hello, I am new to the forums and only recently started using MS Projec
2003.
I am wondering how I would go about the following:
First a bit of history, we track our projects from a single date thi
date really is not a start or a finish but more of a work date.
When we do this we go forwards and backwards in time by using + and
d
Example say our project is supposed to start on 1 Jan 08, before tha
can start we must start a test plan and many other steps.
So our Finish date (for lack of better things to call it) is 1 Jan 0
our Test plan is built - 120 days so that would be 1 Sep 07. Likewis
we do a report that is due + 90 days so that would be 1 Apr 08.
How would I use this as a formula to calculate the dates these need t
start for me.
I envision a task sheet with fields labled
Task Name Duration Lag/Lead Start Date Finish Date
Where Duration would be typed in and lead to a finish date based on th
Lag/Lead column inputting to the Start date
Example
Task Name
Test Plan 20d -120d (calculated Finish dat
-120d = 1 Sep 07) 21 Sep 07
Any ideas on how to build the formula and put it into a column?
I apologize, if this has been asked a zillion times and also for m
newbie'sm
Cheers
2003.
I am wondering how I would go about the following:
First a bit of history, we track our projects from a single date thi
date really is not a start or a finish but more of a work date.
When we do this we go forwards and backwards in time by using + and
d
Example say our project is supposed to start on 1 Jan 08, before tha
can start we must start a test plan and many other steps.
So our Finish date (for lack of better things to call it) is 1 Jan 0
our Test plan is built - 120 days so that would be 1 Sep 07. Likewis
we do a report that is due + 90 days so that would be 1 Apr 08.
How would I use this as a formula to calculate the dates these need t
start for me.
I envision a task sheet with fields labled
Task Name Duration Lag/Lead Start Date Finish Date
Where Duration would be typed in and lead to a finish date based on th
Lag/Lead column inputting to the Start date
Example
Task Name
Test Plan 20d -120d (calculated Finish dat
-120d = 1 Sep 07) 21 Sep 07
Any ideas on how to build the formula and put it into a column?
I apologize, if this has been asked a zillion times and also for m
newbie'sm
Cheers