I am a newbie in MS Project. I have a list of tasks and their
respective durations. I need to assign resources which are equipments
to these tasks. How should i start or from where shoul i start. I need
your help.

Thanks
 
R

Rod Gill

Hi,

Create and assign equipment just as if they were people. Help will explain
how.

--