S
shawn
To all
Please forgive this newby question but I have been trying for a while to
figure it out with little success.
I have an activity : lets say the activity is to move a pile of gravel. The
pile is 10 tons and I can move 1 ton per day on average. How do I create
this activity in project where i can enter the tons and the resource to move
the pile and it will give me a duration. The next activity after that one is
another pile that is a different tonnage (say 12.6 tons).
The question is .. where do I put the tonnage into the activity? Is it a
material resource or something along those lines.. it is not very clear in
MS Project where you can place the amount within the activity?
AHGA!
Shawn
(e-mail address removed) (remove the remove to email to me.. thanks!)
Please forgive this newby question but I have been trying for a while to
figure it out with little success.
I have an activity : lets say the activity is to move a pile of gravel. The
pile is 10 tons and I can move 1 ton per day on average. How do I create
this activity in project where i can enter the tons and the resource to move
the pile and it will give me a duration. The next activity after that one is
another pile that is a different tonnage (say 12.6 tons).
The question is .. where do I put the tonnage into the activity? Is it a
material resource or something along those lines.. it is not very clear in
MS Project where you can place the amount within the activity?
AHGA!
Shawn
(e-mail address removed) (remove the remove to email to me.. thanks!)