M
Matt Kennedy
I have a task in a project that I nned to set to run 24x7 (data migration
load into a new production system). I was expecting to use the standard 24
hour calendar that is normally available in project. If I don't connect to
the server and "work offline" I have that standard 24 hour calendar available
to me as a selection. If I connect to the server all I see is the Standard
calendar. I did have the server configured to not allow the use of local
calendars. I changed that so that local calendars are now allowed. Can anyone
tell me how/where to find the standard 24hr calendar?
I guess I could create my own local 24hr calendar at this point but I am not
sure what the settings need to be as follows: (does anyone know?)
1. Default start time (change start to 0:00am?
2 Default end time (change to 11:59pm?)
3. Hours per day (this is easy 24 right?)
4. Hour per week (again easy 168 right?)
5. Days per month (not sure here - this varies from 28 - 31?????)
Thanks for the help!
-Matt
load into a new production system). I was expecting to use the standard 24
hour calendar that is normally available in project. If I don't connect to
the server and "work offline" I have that standard 24 hour calendar available
to me as a selection. If I connect to the server all I see is the Standard
calendar. I did have the server configured to not allow the use of local
calendars. I changed that so that local calendars are now allowed. Can anyone
tell me how/where to find the standard 24hr calendar?
I guess I could create my own local 24hr calendar at this point but I am not
sure what the settings need to be as follows: (does anyone know?)
1. Default start time (change start to 0:00am?
2 Default end time (change to 11:59pm?)
3. Hours per day (this is easy 24 right?)
4. Hour per week (again easy 168 right?)
5. Days per month (not sure here - this varies from 28 - 31?????)
Thanks for the help!
-Matt