A
AlexM
Hello all,
I have a project that is gives the following error when being opened:
'No calculations can be performed now.
There is a circular relationship in task 136 End of Quarter if
"FY09_Q1_CENTRAL.Published". The successors of this task refer back to
this task or its predecessors, causing a circular reference.
To remove the link that is causing the circular reference, select the
two tasks that are cauasing the circular link, and then click Unlink
Tasks on the Standard toolbad.'
After clicking OK to this error the task gantt chart opens with none
of the tasks showing. This prevents managers from managing any of the
tasks in the project. However when looking at resource view of
assignments I can see all the tasks, or even viewing the project on
Project Web Access.
The task the error is referring to is the last task in the project,
and is unassigned. It is not linked to any other tasks nor are any
other tasks linked to it.
Any ideas on this situation?
-Alex M.
I have a project that is gives the following error when being opened:
'No calculations can be performed now.
There is a circular relationship in task 136 End of Quarter if
"FY09_Q1_CENTRAL.Published". The successors of this task refer back to
this task or its predecessors, causing a circular reference.
To remove the link that is causing the circular reference, select the
two tasks that are cauasing the circular link, and then click Unlink
Tasks on the Standard toolbad.'
After clicking OK to this error the task gantt chart opens with none
of the tasks showing. This prevents managers from managing any of the
tasks in the project. However when looking at resource view of
assignments I can see all the tasks, or even viewing the project on
Project Web Access.
The task the error is referring to is the last task in the project,
and is unassigned. It is not linked to any other tasks nor are any
other tasks linked to it.
Any ideas on this situation?
-Alex M.