No data showing in “% Complete†filed in PWA.

J

Joe

I put “% Complete†as a field in the timesheet view. This field is blank for
the users in PWA, but not on the project plan itself. Any reasons why this
is happening?
 
D

Dale Howard [MVP]

Joe --

The % Work Complete field already shows in the Timesheet view in PWA. If
you really need to add the % Complete field as well, do the following:

1. Open each project in the database
2. Click Tools - Customize - Published Fields
3. Copy the % Complete field to the list on the right
4. Click OK
5. Click Collaborate - Publish - Republish Assignments
6. Click OK

Doing so will "push" the data into the % Complete column on each user's
timesheet.
 